News Release Date
04-30-2026
Beginning March 16, the Colorado Department of Transportation and contractor HEI Civil will begin work to replace the bridge on CO 86 in Kiowa. This $5.1 million project is expected to be completed by winter 2026.
During construction, traffic will be shifted onto a temporary shoofly detour next to the bridge so crews can safely complete the work while keeping CO 86 open.
Please plan for changing traffic patterns, reduced speeds, and temporary detour conditions in the area. We encourage everyone to slow down, use extra caution, and watch for crews and signage.
To receive weekly updates on the CO-86 Bridge construction project, please visit the link below and subscribe to have updates sent to your email every Friday with information on what to expect in the coming week:
http://codot.gov/projects/co86kiowabridge, call (719) 749-7426 or email co86bridge [at] emailtheteam.com (co86bridge[at]emailtheteam[dot]com)
Staying informed will help you plan ahead for traffic changes, potential delays, and any impacts to your daily travel. These updates are a great way to stay aware of project progress and minimize disruptions to your routine.
UPDATES
June 29, 2026 - New traffic pattern in place, detour around bridge, girder removal; Bridge closed, two lane detour open around the bridge, no closures on the detour are planned.
June 22, 2026 - New traffic pattern in place, detour around bridge, girder removal; Bridge closed, two lane detour open around the bridge, no closures on the detour are planned.
June 15, 2026 - New traffic pattern in place, detour around bridge, bridge demo; Bridge closed, two lane detour open around the bridge, no closures on the detour are planned.
June 8, 2026 - New traffic pattern in place, detour around bridge, bridge demo; Bridge closed, two lane detour open around the bridge, no closures on the detour are planned.
June 1, 2026 - Beginning bridge demolition, hauling materials, new traffic pattern; Possible new traffic pattern starting on Saturday, May 30, depending on weather. Traffic switched from bridge to shoefly detour.
May 25, 2026 - Placing material, possibly paving on Wednesday to Friday; Shoulder closures on WB lanes, possible WB lane closures Wednesday 5/27 - Friday 5/29, 7am to 5pm with flaggers holding traffic periodically
May 18, 2026 - Placing material, possibly paving on Wednesday/Thursday; Shoulder closures on WB lanes, possible WB lane closures Wednesday 5/20 & Thursday 5/21, 7am to 5pm with flaggers holding traffic
May 11, 2026 - Building up material for detour around Hwy 86 bridge; Shoulder closures on WB lanes, possible WB lane closures all week, 7am to 5pm with flaggers holding traffic periodically